Prapanca Viaduct, Indonesia

Project Description:
Segmental erection has been carried out for the total bridge length of 1.5 km with 38 nos. of T-spans, 50T to be the heaviest segment & the longest span to be 50m

Builder:
- PT ModernWidya Technical
- PT Hutama Karya (Persero)

Engineer:
PT Perentjana Djaja

Year of Completion: 2015

Involvement:
- Erection of precast box segments via balanced cantilever method using lifters
- Supply of lifters for installation of box girder segments
- Supply & installation of system formworks for stitching
- Design, fabrication, installation, commissioning & operating the lifters & formwork system
- Geometry control