Gyaing Kawkareik Bridge, Myanmar

Builder: Hazama Ando & PS Mitsubishi Joint Venture

Engineer:
- Central Consultant Inc
- Eight-Japan Engineering Consultant Inc
- Japan Bridge & Structure Institute Inc
- Katahira & Engineers International
- Nippon Engineering Consultants Co Ltd
- T.O.P Engineering Consultants International Co Ltd

Year of Completion: 2022

Involvement:
- Main sub-contractor for the construction of Superstructure & Pylon
- Supply & installation of Post-Tensioning works
- Supply & installation of formwork & falsework systems
- Supply & installation of form traveller systems

Construction Methodology:
Balanced cantilever segmental cast-in-situ by Form Traveller Systems

Project Description:
- Type: Extradosed Bridge with Corrugated Steel Web
- Total bridge length: 380m
- Superstructure: Composite Box-Girder with Corrugated Steel Web, Pre-casted Strut and Concrete Slabs (4.8/8.0m length x 22.290m width per segment)

About The Bridge:
The Gyaing Kawkareik Bridge is a four-lane extra-dosed bridge, which crosses the Gyaing River connecting the Ayewady Region, Bago Region, Taninthayi Region, Mon State and Kayin State to the Myawady border trade point.

It is part of the East-west Economic Corridor Improvement Project which targeted to provide better road connectivity from Mawlamyine, Myanmar to Danang City, Vietnam crossing Thailand, Laos and Cambodia.

The bridge is Myanmar’s first composite corrugated steel web extradosed bridge and will replace the existing old Gyaing Bridge which was built in 1997.