Dhaka MRT CP-05, Bangladesh

Special Bridges Details:

- Number of special bridges: 2 nos
- Construction method: Cast in situ balanced cantilever method
- Equipment used: Balanced cantilever form-traveller
- Span length of bridges: 50m-80m-50m (on-going) & 45m-70m-45m (not yet started)
- Maximum capacity of form-traveller: 50 tons
- Minimum curve radius: 200m
- Maximum segment length: 4.0m
- Maximum segment depth: 4.5m
- Segment width: 9.8m

Builder: Tekken Corporation - Abdul Monem Limited - Abe Nikko Kogyo JV (TAAJV)

Engineer: NKDM Association

Year of Completion: 2022

Involvement:

- Supply & operation of launching gantry, form traveller & precast segment mould
- Supply & installation of Post-Tensioning works
- Installation of precast parapet
- Construction engineering services
- Secondment of casting yard specialist
- Secondment of segmental erection specialist.
- Secondment of balanced cantilever bridge construction specialist