Jakarta International Stadium, Indonesia
Builder: WIKA Gedung PP Jaya Konstruksi KSO
Engineer: LAPI ITB
Year of Completion: 2021
Involvement:
- Peer review and Supervision of synchronized heavy lifting system
- Supply & install Laser monitoring system
- Supply & install Strain monitoring system
Construction Methodology:
The stadium’s roof was lifted using a synchronized heavy lifting system with 16 strand jacks, monitored centrally to ensure precision with a maximum deviation of only ±50 mm.