Prapanca Viaduct, Indonesia

Segmental erection has been carried out for the total bridge length of 1.5 km with 38 nos. of T-spans, 50T to be the heaviest segment and the longest span to be 50m

Builder:
- PT ModernWidya Technical
- PT Hutama Karya (Persero)

Engineer:
PT Perentjana Djaja

Involvement:
- Erection of Precast Box Segments Via Balanced Cantilever Method Using Lifters
- Supply of Lifters for Installation of Box Girder Segments
- Supply and Installation of System Formworks for stitching
- Design, Fabrication, Installation, Commissioning & Operating the Lifters and Formwork System
- Geometry Control

 