Builder: Sato Kogyo (S) Pte Ltd
Engineer: YWL Engineering Pte Ltd
Year of Completion: 2010
Involvement:
- Supply & installation of Post Tensioning works
- Lifting & installation of precast segments
- Design, supply & operating of PC segment hanger
Project Description:
Longest span: 70.5m
Construction Methodology:
Balanced cantilever segmental construction